Site and Infrastructure Phase 6 was a campus wide project completed key phases of work related to the campus Clean Water Act Section 404 permit granted by the US. Army Corps of Engineers, including:
- Construction of a dirt perimeter road to improve access to the outer areas of the campus and community;
- Construction of boundary fences between the campus and natural reserve lands;
- Mass grading to improve storm water management;
- Construction of a kit fox bridge; and
- Salvage of impacted wetland soils
Project Manager: Wenbo Yuan
Completion Date: 2013