Skip to content

Construction Updates

January 2014
Student Services Building - three story section - opens
 
August 2013
Housing 4 - Half Dome opens to its first residents
Student Services Pavilion opens for Fall 2013 semester 
 
April 2013
Housing 4: Exterior skin applied, finishes installed, permanent power activated March 23
Science and Engineering 2: Building exterior wall work ongoing, concrete deck pours conducted in March.
Student Services Building: Pavilion exterior and roof deck completed. Waterproofing and curtainwall in April
 
February 2013
Student Services Building: Topping off ceremony held on Feb 15
 
January 2013
Science and Engineering 2: Topping off ceremony held on Jan 18; pre-cast columns and foundation near completion
Housing 4: Elevator and windows installation, bathrooms prepared for tile installation
Student Services Building: Pavilion and three-story concrete slab poured; Pavilion steel structure constructed
 
October 2012
Site demolition, rough grading and trenching underway at Student Services Building
Window framing begins at Housing 4
First floor metal and concrete decking begins at Science and Engineering 2
 
August 2012
Student Activities and Athletics Center (formerly Recreation Center North) opens
Housing 4 holds topping off ceremony
 
July 2012
Science and Engineering 2 basement excavation continues
Steel framing completed on Housing 4; Housing 4 receives official name: Half Dome
Recreation Center North still on track for Fall 2012 opening
 
June 2012
Science and Engineering 2 basement excavation is underway
Steel framing for Housing 4 has begun  
Recreation Center North on track for Fall 2012 opening
 
April - May 2012
Ground breaking for Science and Engineering 2 and perimeter fencing installed
 
February 2012
The steel frame for Recreation Center North erected. Final beam installed Feb. 23
The Kit Fox bridge for Site and Infrastructure Phase 6 was installed on Feb. 21
 
January 2012
Site and Infrastructure Phase 6 began grading and leveling of long-term development sites; project includes perimeter fencing and construction of a Kit Fox bridge as required by the campus's 404 permit 
Recreation Center North project begins pouring concrete for foundation
Housing 4 grading completed and utilities installed